 Infosys has made changes in the EOD execution procedure.  The major changes done by infosys to address EOD issues ar as follows:

1.  SOLs should only run HISCOD menu  ( new menu  available  for PO user - SU, SA, PM )

2.  HSCOD, HSOLCOP and HSCOLD to be executed by CPCs in circle sets
SOL EOD execution comprises of executing HSCOD, HSOLCOP & HSCOLD menu. Please find the current DOP executing procedure and the centralized EOD execution procedure to be followed, 
DOP is following current EOD execution procedure, 


Execution of EOD 1st Menu

HSCOD

Branch User will be executing after clearing the blocking validation

Execution of EOD 2nd Menu

HSOLCOP

Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSCOD is completed for their SETs

Execution of EOD 3rd Menu

HSCOLD

Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSOLCOP is completed for their SETs
This has to be changed to Centralized EOD execution procedure, 


Submission of Pre EOD Menu

HISCOD

Branch User will be submitting after clearing the blocking validation

Execution of EOD 1st Menu

HSCOD

CPC User will be executing with optimal parallelization as 20 once HISCOD is submitted for their SETs

Execution of EOD 2nd Menu

HSOLCOP

Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSCOD is completed for their SETs

Execution of EOD 3rd Menu

HSCOLD

Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSOLCOP is completed for their SETs
 During EOD execution, the overall EOD progress for the Circle to be monitored & co-ordinated by CPC team centrally.
Please find the procedure to be followed by Branch user for Submitting Pre EOD menu, 
·        Invoke HISCOD (Initiate SOL Change Operation Date) menu
·        Provide the SOL ID under the field “SOL SET ID”, Hours as 0 & Minutes as 1
·        Submit

Please find the procedure to be followed by CPC user for SOL Date Change Execution,
·        Invoke HSCOD (SOL Change Operation Date) menu
·        Provide the Circle SET ID under field “SOL SET ID”
·        Provide Optimal Parallelization under field “No. of Parallel SOLs”
·        Submit
CPC user can inquire lists of SOLs where HISCOD submitted for their Set through HSSI menu.
CPC user can inquire the HSCOD running status for their Set through HSSI menu.
The EOD Status of particular SET or for all SOLs can be monitored through HSSI menu. 